Work Item Life Cycle

Brand Guidelines Style Guide Working Group Lifecycle Work Item Lifecycle Github Donation Spec Tooling Guides Code of Conduct

Note: this overview was created by combining section 7 of the underlying JDF charter with the October 2020 addendum to be readable as a consolidated overview. It is not an authoritative document, so if you find any discrepancies, those two linked documents are the authoritative documents.

Please note: deliverables (code and/or specifications) may be "donated" to DIF at any point in the process below, which describes original work happening inside DIF. For instructions on how to effect a donation, see the Github Donation section.

Deliverable Development Process.

7.1. Pre-Draft.

Any Working Group Participant or Contributor may submit a proposed initial draft document as a candidate Draft Deliverable of that Working Group. The Working Group chair will designate each submission as a “Pre-Draft” document.

  1. A Pre-Draft MAY BE referred to as a “Straw man” internally
  2. Additional “Straw men” can serve as input documents to a Draft Deliverable, in part or in whole, and can be submitted after a Draft has been initiated at the discretion of the chairs.
  3. If a deliverable builds on prior art designed and/or built by a participant in the DIF work in a legally significant way, i.e., if one or more input documents to the DIF work could constitute a threat to the IP safety of the DIF work item, the Working Group MAY request that it be officially donated to DIF before acceptance of the work item, such that IP rights (and ongoing maintenance) of the legacy work can be brought into the remit of the group. Review by the Executive Director and/or the Technical Steering Committee may help to clarify the scope or procedure for this donation in case of conflicts over this request.

7.2. Draft.

Each Pre-Draft document of a Working Group must first be Approved by the Working Group Participants of that Working Group to become a Draft Deliverable. Once the Working Group approves a document as a Draft Deliverable, the Draft Deliverable becomes the basis for all going forward work on that deliverable.

  1. Versioning of specifications or code SHALL apply to every change affecting normative statements and/or test vectors.
  2. All released versions of a draft SHALL be accessible at a static and permanent URL, tracked by DIF. (This is to minimize risk of editorial error or “overwriting” of significant changes).
  3. Work items or their groups MAY customize the standard contributor guidelines template. SemVer.org-conformant versioning is the expectation, and if other conventions will be used, guidance should be published in the governing contributor guidelines document.

7.3. Working Group Approval.

Once a Working Group believes it has achieved the objectives for its deliverable as described in the Scope, it will progress its Draft Deliverable to “Working Group Approved” status.

  1. Where protocols or interfaces are being specified, a section explicitly defining test vectors for conformance testing SHALL be written at time of approving a draft or earlier.
  2. The WG approval process is a good time to do a final call for significant contributors to PR into the deliverable any entries to an "Acknowledgments" section of the deliverable (readme.md for code deliverables). This is recommended in cases where non-recurring, equity free forms of funding supported the work (i.e. "grants" or other research and public-good support including DIF itself). Each supported contributor is responsible for their own acknowledgement. For a template, see the [Acknowledgement Template](#Acknowledgement-Template) section below. If the WG chairs and membership cannot come to agreement about specific acknowledgements, this can be escalated to the Technical Steering Committee by either party.
  3. Before Steering Committee Approval, the approved version should be placed at a permanent link tracked on DIF’s spec-tracking github repo. See Presentation Exchange v1.0.0 for an example. This includes:
    • In the spec repo, create a subfolder under the spec folder named version_number
      • For Presentation Exchange v1.0.0, that results in spec/v1.0.0/
    • Copy the WG approved spec.md file to the newly-created subfolder
    • For Presentation Exchange v1.0.0, spec/spec.md was copied to spec/v1.0.0/spec.md
    • In the copied version, ensure the spec's version and specification status are up to date.
      • In the file spec/v1.0.0/spec.md, the following updates were made:
      • Title: Presentation Exchange v1.0.0
      • Specification Status: DIF Ratified Specification
  4. The WG Chair requests SC approval.

7.4. Final Approval.

Upon a Draft Deliverable reaching Working Group Approved status, the Executive Director or his/her designee will present that Working Group Approved Draft Deliverable to the Steering Committee for Approval. Upon Approval by the Steering Committee, that Draft Deliverable will be designated an “Approved Deliverable.”

  1. Once WG Approval has been achieved, the chairs should use the Technical Steering Committee email list to notify it that SC approval will soon be sought; a one-week response time is customary for this review request. If the Technical Steering Committee believes there may be cause for the Steering Committee to withhold approval, they should formulate clear and actionable change requests for the group; delaying SC approval to address such requests is advised in such cases.
  2. Final approval by DIF is referred to as “DIF Ratified Deliverable" or "DIF Ratified Specification” internally.
  3. The steering committee MAY invite external review of test vectors and normative statements at this point, regardless of whether the Draft will proceed to step 7.6 or only to step 7.5

7.5. Publication and Submission.

The Executive Director will publish the Approved Deliverable in a manner agreed upon by the Working Group Participants (i.e., Project Participant only location, publicly available location, Project maintained website, Project member website, etc.).

Publicly-available specifications will be added to DIF's spec tracking repo

The publication of an Approved Deliverable in a publicly accessible manner must include the terms under which the Approved Deliverable and/or source code is being made available under, as set forth in the applicable Working Group Charter.

7.6. Submissions to Standards Bodies.

No Draft Deliverable or Approved Deliverable may be submitted to another standards development organization without Approval by the Steering Committee. Upon Approval by the Steering Committee, the Executive Director will coordinate the submission of the applicable Draft Deliverable or Approved Deliverable to another standards development organization with Joint Development Foundation Projects, LLC. Working Group Participants that developed that Draft Deliverable or Approved Deliverable agree to grant the copyright rights necessary to make those submissions.

Work Item

A work item can be considered a DIF work item once the status of the item reaches one of the stages mentioned in the Deliverable Development Process (above). Each DIF work item must be concluded and developed under the https://github.com/decentralized-identity organization's repository to be considered part of the Deliverable Development Process, making it a DIF work item.

Types of Work Item:

Specification

The most common output of working groups at DIF are specifications, which unambiguously define and specify distinct protocols, data models, and/or functional software modules.

Specifications may also be versioned updates of previously published specifications.

Profile

A work item that only describes and/or implements a subset of one or more existing normative specifications, whether standards-track or DIF-terminal (such as, say, Presentation Exchange or DIDComm) can be called a "profile", not a specification, in that all normative and IP-sensitive work is done by an existing specification, making this a "derivative work" and not needing IPR protection. It is recommended that detailed profiles of a single DIF work item or deliverable be donated to the working group that defined that work item to simplify IP concerns if the contributors defining the profile need to open an "upstream" PR or issue. See the profile template here

Interoperability Profiles

A common goal for interoperability efforts is to define a profile of multiple specifications (protocols and/or data models) that add up to an "end to end" profile for use by a certain ecosystem or infrastructure. These can, ideally, be defined without any new IPR-sensitive contributions or ideas, whether in a non-IPR-protected group like the Interoperability WG or elsewhere and donated to DIF. There always exists, however, the possibility that the reality is less tidy than the ideal, and such a multi-spec profile finds itself specifying more than zero or accepting contributions that seem substantial in retrospect. For this reason, all working group chairs should review any such donations critically with this very issue in mind, and, if needed, work with donators to open a work item in an IPR-protected working group to resolve any ambiguities about the IPR status of all inputs to a profile if they are not confident that an interop profile is adequately descriptive and non-normative to constitute an IPR-safe donation before it goes to the Technical Steering Committee for DIF ratification.

Registry

In some cases, an ongoing work item can be created that collects inputs, such as a directory or registry of links to downstream projects or governance authorities. To minimize reputational risk or market confusion that could occur from such open-ended registries bearing an implicit DIF seal of approval, registry work items must define the process for registering items, this process should be approved by working group chairs (and at discretion of same, the DIF steering committee) before being opened up to outside PRs. Once approved, editors (i.e. code owners) of a given registry are encouraged to merge PRs and grow their registry indefinitely within the guidelines of the approved process, while relying on working group chairs in case of uncertainty about incoming registrations and, of course, to ensure continuity of maintenance. See the registry template here

Maintained versus Archived Work Items

Regardless of how far it proceeded through the statuses above, any DIF work item is presumed to be an ongoing work item under active management unless explicitly marked as "Archived" by the Working Group managing it.

If open issues are growing stale or not being handled within a reasonable amount of time, WG chairs may contact work item leaders to request more consistent management, and if this is not forthcoming, may move to mark the work item as "Archived". In leiu of active chairs, the technical steering committee could also intervene in that capacity.

The process for archiving is simple: WG chairs request that DIF staff mark the repo as archived in github, and that the change be reflected on DIF's website. It is recommended that a sentence about the new archival status also be added to the rendered/hosted spec and repo "README.md" file.

Once archived, WG chairs should check their WG's home repo or other informative references to ensure that archived work items aren't listed among ongoing work items.

Acknowledgement Template

{ENTITY_NAME} received funding from {FUNDING_SOURCE} to contribute to this work item. {OPTIONAL DETAILS ABOUT SCOPE, CONTRACT NUMBERS, OVERSIGHT, ETC}. This work item does not necessarily reflect the position or the policy of {FUNDING_SOURCE} and no official endorsement of the work item or of DIF itself should be attributed to {FUNDING_SOURCE} on the basis of this support.