We can start getting ready to release a new version whenever all issues and pull requests related to a milestone are completed.

Before releasing a new version, the following tasks need to be done:

  • Integration tests: the whole team is involved (Those who perform tests must fill out this form.)
  • Generate the SDK
  • Upload in Artifactory
  • Upload in S3 (Amazon Server)
  • Test the SDK again
  • Write the changelog:
  • Update JAVADOCS
  • Update the SDK download links in enterprise area and documentation
  • Update samples in TotalCross repositories for the new version (and update retrolambda version on pom.xml)