Iter 6

Closed Aug 1, 2021 100% complete

Following are the planned deliverables.

  1. Completion of ops for Snapshot, AFR, Arbiter and Glusterfind.
  2. Completion of TC migration of components, Glusterfind, Arbiter, Authentication and Snapshot.
  3. Addition of signal handling component.
  4. Doc changes to reflect latest changes.

Milestone status.

  1. AFR, Arbiter and Glusterfind ops have been completely added. Sc…

Following are the planned deliverables.

  1. Completion of ops for Snapshot, AFR, Arbiter and Glusterfind.
  2. Completion of TC migration of components, Glusterfind, Arbiter, Authentication and Snapshot.
  3. Addition of signal handling component.
  4. Doc changes to reflect latest changes.

Milestone status.

  1. AFR, Arbiter and Glusterfind ops have been completely added. Scheduler ops is pending in snapshot.
  2. Migration of Glusterfind, auth and arbiter has been completed. Snap and afr are still in progress.
  3. Signal handler analysis has been done but design and addition has not been done.
  4. Doc changes have come along with the latest fixes.

Unplanned enhancements which were added.

  1. Multi brick disk feature added. Though further additions will be required.

Tasks which will overflow to the next milestone.

  1. Scheduler ops in snapshot.
  2. Test migration for AFR and Snapshot.
  3. Signal handler during redant process kill.

This milestone is closed.